Latest updates

27 Feb 20

Lift

We're putting in a lift from the ground floor café so visitors can access the Great Chamber on the first floor. This week the contractors began work on the shaft for this lift.

18 Feb 20

Pathworks

The visitor path between the car park and manor is almost complete.

10 Feb 20

Joinery

The new visitor toilets are being installed, joinery is almost complete.