Skip to content

Our work: Millbrook footbridge and tumbling bay weir

The weir at Millbrook in full flow
Millbrook weir in full flow | © National Trust/Nina Elliot-Newman

The River Wey and Godalming Navigations bring together a network of 16 locks, 13 weirs, 56 bridges, 11 mooring lines and 20 miles of towpath, along with many other structures. The tumbling bay weir and footbridge at Millbrook sit within the vast network, as just one of many parts of the navigations the National Trust looks after.

Guildford's much-loved weir

Millbrook tumbling bay weir lies in the very heart of Guildford town centre. It is believed that there has been a weir on the site since the 12th century, put there by mill owners to control the water levels in the 'pound' above in order to power their mill wheels. Today, the weir plays an important role in maintaining water levels along the River Wey.

Project delivery

The weir collapsed in 2019, along with the footbridge, and a temporary weir structure was installed. We appointed contractors Knights Brown this year to replace both the weir and the bridge.

The work involves use of a contractor’s compound in a designated part of the council’s Millbrook car park (off the A281). The navigation will remain open as usual, with only short safety closures for specific activities e.g. when materials are being craned over the water.

November 2026

Latest update

The project enters the final stage

Timeline of work so far

November 2026

The project enters the final stage

The engineering project to replace Millbrook Weir and footbridge is coming to an end, however the bridge will remain closed for a few more weeks while a small section over the sluice gate is built off-site.

This extra section of bridge was identified as needing replacing during the main project, and we decided to carry out this work now rather than close the towpath and footbridge again in the near future. As a result, it will be a few more weeks until the bridge is fully open.

We’d like to thank everyone for their patience. While there may not be work happening on site every day, we are working hard behind the scenes to complete the project and minimise any delays. 

An image of diggers and engineering work taking place on a weir structure on the River Wey
Works taking place on Millbrook Weir and footbridge | © Emma Cooper

Towpath diversion

Throughout the works a short detour remains in place for walkers to rejoin the towpath at Guildford Rowing Club or the Yvonne Arnaud Theatre.  

Map 1 From Millmead Lock                                   

Map 2 From Millbrook Weir (Millmead Lock side)                                   

Map 3 From Millbrook Weir

Map 4 Approaching Millmead from the south   

Map 5 Steps from the towpath, approaching Millmead from the south

 

 

Project background

In 2024 the National Trust tendered for, and commissioned, a feasibility study of Millbrook Weir. Over the drier summer months, a local specialist engineering firm conducted detailed geotechnical and structural investigations. Using the data from these surveys, our engineers designed a replacement structure, which reuses the materials in the current temporary weir as much as possible. 

Throughout 2025 we worked with a variety of agencies and engineers on the plans, as well as tendering for the construction phase of the project, and securing relevant permissions to carry out the works. 

How the structure works

The tumbling bay is a 'fixed crest' weir which allows water to tumble over from one level (or ‘pound’) to the next, giving the site its much loved rushing water sound. The structure also contains a set of three sluice gates which can be raised or lowered manually to adjust water levels. A footbridge previously ran over the weir channel, linking the footpath onto an island of green space, with the towpath continuing beyond. 

Water levels over the weir vary at different times of the year, from a slow trickle in summer to a constant torrent during wetter months, when up to two million litres or water per hour might cascade over the crest.

Thank you

We’d like to acknowledge the support of so many people locally who have expressed to us how much the bridge means to them and campaigned wholeheartedly for it to be reinstated. We share their passion for bringing back this much needed part of Guildford’s heritage. We appreciate their patience and hope for their continued support as we lead the next phase of the project, with a more certain future for Millbrook weir and bridge.

Ensuring equal access to green space, especially in an urban setting like Guildford, is a fundamental aim of the National Trust. We understand the importance of the riverside walks that the Wey Navigation offers to the community of Guildford, and the role that these areas play for wellbeing, socialising, exercise, leisure and enjoying nature. 

Thanks to your ongoing support, we are able to continue our vital conservation work and help to protect these special places.